JCT Design and Build and JCT Standard Building Contracts 2016 – Part II

JCT has published the new edition of 2016 Design and Build Contract in conjunction with the Design and Build Sub-Contract for use with it. The purpose of this note is to outline the principal changes from the previous 2011 edition and answer some frequently asked questions. Part I of this article was published in the February edition of JCT News.

How is Loss and Expense for delay dealt with?

Section 4 which deals with loss and expense still requires prompt initial notification of claims, or the likelihood of claims as before that notification is required “to be accompanied, or as soon as reasonably practicable, followed by the Contractor’s initial assessment of the loss and expense incurred and any further amounts likely to be incurred…”. However, it goes on to provide for monthly updates from the Contractor “for as long as is necessary for final ascertainment”.

These requirements are an attempt to avoid the practice of loss of and expense claims not being made or the particulars of them not being given until late in the project after the events giving rise to delay and consequent loss and expense have long since passed.

JCT has not adopted the approach of some bespoke amendments whereby notification by the Contractor in accordance with a time limit is a condition precedent to entitlement to loss and expense, which means that in principle noncompliance avoids the claim.

The Employer (through the Employer’s Agent in the case of DB and the Contract Administrator in the case of SBC) is required to notify the Contractor of his initial ascertainment within 28 days of receiving the required information from the Contractor with further notifications being made within 14 days of each subsequent update. In each case the Employer/Contract Administrator is required to identify any points on which that ascertainment differs from the Contractor’s assessment.

In the amended JCT provisions not only does the Contractor have to notify circumstances which may give rise to loss and expense and keep the Employer/Contract Administrator updated, but also the Employer (through the Employers Agent/Contract Administrator) should not be able to leave loss and expense to one side pending practical completion.

The Relevant Matters which give rise to loss and expense are unchanged and still include Changes to the Employers Requirements (in the case of DB) or Variations (in the case of SBC).

However, loss and expense is now to be included in the valuation of a Change in DB if the procedure set out in Supplemental Provision 24 (Valuation of Changes – Contractor’s Estimates) is used. So clause 4.21 which deals with Changes to the Employers Requirements will only be relevant if Supplemental Provision 24 does not apply.

Any changes to the Final Account Provisions?

Clause 4.12 of DB requires the Contractor to submit the Final Statement to the Employer within three months from practical completion of the Works, as was previously the case. If he fails to do so either within that period or within two months of a reminder notice from the Employer, the Employer may issue the statement. Either way, unless the final balance shown is disputed within the time limits specified by the contract, the statement then becomes conclusive as to the final balance. It then has further conclusive effects in accordance with clause 1.8 (materials, goods and workmanship being to the Employer’s Requirements standards, extensions of time given and loss and expense awarded) except where and to the extent that proceedings have been instituted and until those claims have determined.

Clause 4.25 of SBC deals with the final adjustment and final payment. The relevant Quantity Surveyor statement and ascertainment is to be provided to the Contractor, within 3 months of the Contractor providing the relevant documentation. That documentation is to be supplied within a maximum of 6 months after Practical Completion of the works. Clause 4.26 then deals with the issue of the Final Certificate.

That Final Certificate must be issued within 2 months of the last of the end of the Rectification Period of the Works, the date of issue of the Certificate of Making Good Defects or the date on which the Contractor is sent the Final Certificate. Then the Final Certificate has the same conclusive effects under Clause 1.9 as referred to above regarding Clause 1.8 of DB.

What changes have been made to the insurance provisions?

There remains three principal Joint Names Works Insurance Options (A, B and C). However, Option C, which usually applies where there are existing structures, has been amended so as to allow alternative (non JCT prescribed) solutions for existing structures and contents cover to be adopted through a Replacement Schedule. This is an attempt to provide flexibility where works are being undertaken in only part of a multiple occupancy building. In such circumstances it can be difficult for the Employer to obtain Contractors All Risks cover because of the risk of a specified peril such as a fire starting with the works and also causing damage to neighbouring properties or their contents in the rest of the building.

Works Insurance may also not be available for works carried out by tenants where insurance of the existing structures is the landlord’s responsibility.

Often the value of the works themselves and the additional risk in respect of the structures and contents of the rest of the building is within the cover that a contractor has or can obtain under the contractor’s public liability insurance. However where a tenant-employer is in a building in multiple occupancy, the overall value of the structures for the whole of the building and contents belonging to the other tenants or the Landlord, may be beyond the contractor’s public liability cover. Where this is the case alternative insurance arrangements involving different layers of cover and risk may be necessary. Such insurance becomes more complex the higher the value of the works and the greater the risks to the adjoining properties. Where the potential liabilities to the contractor exceed any agreed level of cover, the contractor may require an indemnity from the Employer in respect of any claims above those agreed limits.

Where there are existing structures on site but they consist of the building shell or retained façades that have a reinstatement value substantially less than the value of the works to be undertaken, the contractor’s works insurers may be prepared to extend Option A cover to include such structures and this is worth exploring before investigating alternative Option C cover.

It is therefore very important that a prospective employer seeks special insurance advice ideally prior to tender. Any employer-tenant should also consult his landlord on the insurance arrangements.

Any change to the provisions relating to terrorism cover?

No. The position remains that often joint names or risks cover of the Works excludes cover for acts of terrorism apart from (depending on the terms of the cover) a small level of cover. Accordingly terrorism cover needs to have been specifically required and an appropriate entry to this effect needs to be made in the Contract Particulars. This can be under the Pool Re scheme or other cover such as that provided by the Lloyds market. However, the terms of the cover should be checked carefully. Lloyds market cover does not include chemical and biological damage. Pool Re cover excludes nuclear, chemical and biological risks in respect of a residential property. Pool Re cover also always requires annual renewal. However, Lloyds market cover may be available on a project basis.

Does the contract require evidence of insurance to be provided?

Helpfully the provisions relating to evidence of insurance previously set out in each of the three Works Insurance Options are now consolidated into Section 6 and the insuring party is required to provide evidence of cover as the other party reasonably requires within seven days of a request to do so.

How are performance bonds and guarantees dealt with?

If a parent company guarantee or performance bond (or conceivably both) are required an appropriate entry will be made against Section 7 in the Contract Particulars. The new enabling provisions are dealt with in section 7 of each Contract which previously dealt only with assignment, third party rights and collateral warranties. This is a welcome addition as previously the requirement for such security from a contractor had to be added by way of amendment to the standard form.

What are Third Party Rights (TPRs) and how have they been amended in the Contract?

TPRs are an alternative to standalone collateral warranties. They are in similar terms to collateral warranties but importantly can be invoked simply by serving a notice on the party giving the warranty rather than that party having to execute a collateral warranty. In practice sub-contractor warranties are often difficult to obtain. Unlike other design parties on a project, design sub-contractors may be engaged as the works progress and the collateral warranty requirements can be overlooked or sought later when a sub-contractor has left site. JCT has now included as an option TPR’s from sub-contractors which if used may reduce these difficulties. Previously the 2011 edition only provided for TPR’s from the contractor.

JCT TPR’s comprise Rights Particulars and Rights Conditions. As stated above the former part 2 of the Contract Particulars (in which the Contractor Rights Particulars were previously dealt with) has been deleted. JCT has also made certain other amendments as follows:

  • the provisions in relation to professional indemnity insurance have been harmonised so that the provisions are the same in both the JCT standard collateral warranties in favour of a purchaser tenant and funder, as they are under the TPR’s. Therefore the beneficiary of a warranty or the TPR’s (as the case may be) will automatically receive an undertaking from the Contractor in relation to such insurance in the same terms as those given to the employer under the main contract. However, in sub-contracts it is still necessary for the employer in his Rights Particulars to specify the level of professional indemnity or product liability cover (as the case may be) that the contractor is to require from various sub-contract trades.
  • there is now a net contribution clause included in the terms of the TPR’s from the contractor and the JCT contractor warranties.
  • a default provision has also been added (in clause 7.4.2) so that where the Employer or Contractor (as the case may be) has failed to specify whether rights are to be granted to a beneficiary by TPR’s or a collateral warranty. In that case the grantee contractor or sub-contractor can choose how to provide the rights whether by TPR’s or a warranty.

Will Schedules of Amendments to the JCT terms still be used?

We anticipate that the answer is yes. Whilst JCT have addressed some of the amendments commonly made in the market, they have not included the principal amendments often sought by Employers.

In respect of DB (and the design portion of SBC) these often require the Contractor to accept full design responsibility. This may involve the novation of design consultants to the Contractor. As yet there is not a JCT novation agreement nor any operative provisions allowing for it in the new form. It is generally the case that under an unamended JCT DB Contract (and SBC design portion) the Contractor does not take full design responsibility. The Contractor is liable for the Contractors Proposals only in response to the Employers Requirements.

Many main contractors also amend the JCT subcontracts to reflect their standard terms as well as to step down amendments made to the main contacts terms and conditions.

 

Suzanne sits on the JCT Drafting Subcommittee and JCT Council. She is Head of Construction at Wedlake Bell Solicitors.

Suzanne’s practice covers all issues relating to construction projects including contract drafting and dispute advice and resolution.

Suzanne has over 25 years’ experience in the construction industry dealing with both contract drafting and disputes (domestic and international), acting for most sectors of the industry and involving and wide range of projects large and small, such as house building, office and retail development, manufacturing plant, hospitals, sports stadia and infrastructure.

Blog Author: Suzanne Reeves – Partner, Wedlake Bell